Journal of the Korea Institute of Military Science and Technology 2006;9(2):60-69.
A Study on Improvement of Defense R & D Program by PMB
Seok-Cheol Choi, Yun-Ho Bae
1KNDU
2DAPA
PMB적용을 통한 국방연구개발 사업관리 개선방안 연구
최석철, 배윤호
1국방대학교 무기체계학과
2방위사업청 획득기획국
Abstract
The PMB(performance measurement baseline) is the total time-phased budget plan against which program performance is measured. Additionally it is the schedule for expenditure of the resources allocated to accomplish program scope and schedule objectives, and is formed by the budget assigned. In this paper, we suggest an improvement of the R & D(research and development) program for defense acquisition by using the PMB and an application of the IBR(integrated baseline review) to review the PMB for project manager of the defense agency.
Key Words: PMB, EVMS, IBR, ERP


ABOUT
ARTICLE CATEGORY

Browse all articles >

BROWSE ARTICLES
FOR CONTRIBUTORS
Editorial Office
160 Bugyuseong-daero 488beon-gil, Yuseong-gu, Daejeon 34060, Korea
Tel: +82-42-823-4603    Fax: +82-42-823-4605    E-mail: kimst@kimst.or.kr                

Copyright © 2023 by The Korea Institute of Military Science and Technology.

Developed in M2PI

Close layer
prev next