J. KIMS Technol Search

CLOSE


J. KIMS Technol > Volume 21(3); 2018 > Article
Journal of the Korea Institute of Military Science and Technology 2018;21(3):396-402.
DOI: https://doi.org/10.9766/KIMST.2018.21.3.396   
An Analysis of Effect and Limitation when Adapting Earned Schedule Method for Schedule Management and Estimation in Korean Defense Research & Development Projects
Jungho Cho, Jaesung Lim
1R&D Programming Directorate, Agency for Defense Development
2Department of NCW Engineering, Graduate School, Ajou University
한국 국방 연구개발 프로젝트 일정 관리 및 예측을 위한 Earned Schedule 기법의 적용 효과와 한계 분석
조정호, 임재성
1국방과학연구소 연구계획부
2아주대학교 일반대학원 NCW공학과
Abstract
Earned Value Management(EVM) has been used to manage and forecast defense project schedule and cost over the last two decades in the world. However to support the lacking ability of schedule analysis in traditional EVM, earned schedule(ES) has been introduced as a tool to more accurately estimate schedule performance. This paper compares which method EVM or ES, provides more accurate schedule predictors in 32 Korean defense research and development projects. As a result of comparison, the ES method can predict the future schedule more reliably than the EVM method. We also analyze early warning function of schedule performance index considering project duration extension point. Through the analysis results, we confirm that both the EVM and the ES method lack the ability of the early warning in terms of the current schedule management criterion.
Key Words: Earned Value Management, Earned Schedule, Schedule Performance Index, Schedule Estimate at Completion


ABOUT
ARTICLE CATEGORY

Browse all articles >

BROWSE ARTICLES
FOR CONTRIBUTORS
Editorial Office
160 Bugyuseong-daero 488beon-gil, Yuseong-gu, Daejeon 34060, Korea
Tel: +82-42-823-4603    Fax: +82-42-823-4605    E-mail: kimst@kimst.or.kr                

Copyright © 2025 by The Korea Institute of Military Science and Technology.

Developed in M2PI

Close layer
prev next